ERP implementation timeline at a glance
Every Faxtor ERP project runs through the same four phases. Each one ends with something you can see and sign off before the next begins.
| Phase | Duration | What happens | What you get |
|---|---|---|---|
| 1. Discovery | 1–2 weeks | We study how each department works and which software and sheets they use | Process map, module plan |
| 2. Design | 2–3 weeks | We set up your products, prices, approvals and reports, and design the owner dashboards with you | Configured modules, dashboard designs |
| 3. Build | 6–12 weeks | We build what is specific to your business and connect Tally and other tools | Working demos every two weeks |
| 4. Launch | 1–2 weeks | We move in your masters and opening balances, train each department and go live | Data migrated, team trained |
Added end to end, the phases come to 10 to 19 weeks. In practice they overlap: design on later modules continues while the first ones are being built, and modules go live one at a time rather than all on the last day. That is why most projects are live in 8 to 16 weeks.
The four phases in detail
Phase 1: Discovery (1–2 weeks)
Most business owners know their problems but not what is possible in software. So before anything is built, we sit with you and your department heads to map how work moves today: where orders come in, how stock is tracked, who approves what, and which Excel sheets and WhatsApp groups hold it together. You do not fill in a form; we have a real conversation about your business.
Your part: time with the owner and each department head, and copies of the sheets and reports you use now.
Phase 2: Design (2–3 weeks)
We set up the system with your products, price lists, approval rules and report formats, and design the owner dashboards around the numbers you check every day. Because Faxtor builds on FaxtorCore, a shared platform used across more than 20 industries, much of this is configuration rather than new code.
Your part: confirm masters and rules, and sign off the dashboard designs.
Phase 3: Build (6–12 weeks)
We build what is specific to your business, such as custom workflows, pricing logic or production stages, and connect Tally and any other tools you use. You see working software every two weeks, not a big reveal at the end. Feedback from each demo goes into the next two weeks of work.
Your part: attend the fortnightly demo and send feedback within the week.
Phase 4: Launch (1–2 weeks per module)
We move in your customer, product and vendor masters and opening balances, train each department on its own module, and go live module by module. A cut-over date is agreed in advance so the team knows when the old sheets stop and the new system starts.
Your part: make staff available for training and stick to the cut-over date.
Typical timelines by project size
| Project | What it covers | Typical time to go live |
|---|---|---|
| CRM | Leads, follow-ups, deal stages, sales dashboard | About 4 weeks |
| Focused ERP | 2–3 modules, e.g. sales, inventory and accounts | 8–10 weeks |
| Full ERP | 5 or more departments, integrations, owner dashboards | 12–16 weeks |
| Larger builds | Multiple companies, plants or locations | Planned after discovery |
You get a written plan with dates for each module before any build work starts.
A 12-week example, week by week
This is an illustrative plan for a trading business that wants sales, purchase, inventory and accounts with Tally sync. It shows how the phases overlap and how modules go live in stages.
Weeks 1–2 Discovery with the owner, sales, stores and accounts. Process map and module plan signed off.
Weeks 3–4 Products, price lists and approval rules set up. Owner dashboard designed.
Weeks 5–8 Sales and CRM built. Demos in weeks 6 and 8. Purchase and inventory design runs alongside.
Week 9 Sales goes live. Sales team trained; customer master migrated.
Weeks 9–11 Purchase and inventory built and demoed. Inventory goes live in week 11 with opening stock.
Week 12 Accounts goes live with Tally sync and opening balances. Owner dashboard switched on.
By week 9, the sales team is already working in the new system, three weeks before the project is complete.
What slows an ERP project down
When an ERP runs late, the cause is rarely the software. These are the usual reasons.
No single decision maker. When three people must agree on every approval rule, each sign-off takes a week instead of a day.
Scope added mid-build. New modules requested during the build push every later date. Better to note them and add them after go-live.
Messy data. Duplicate customers, inconsistent product names and missing opening balances must be cleaned before import.
Going live everywhere at once. A single big-bang launch puts every department into training in the same week and makes problems harder to trace.
Slow feedback on demos. Each fortnight of delayed feedback can add a fortnight to the end date.
Old software with no way to connect. Some older tools have no API, so data has to be exported and mapped by hand.
What speeds it up
Start with your biggest pain. Pick the one process that irritates you most and go live with that first. Many owners start with a CRM.
Name one owner for the project. One person on your side who can make decisions keeps sign-offs to days.
Clean your masters early. Start tidying customer, product and vendor lists during discovery, not at launch.
Go live module by module. Each department switches over when its module is ready, and the next one benefits from what was learned.
Build on a proven core. FaxtorCore already covers orders, stock, invoices, approvals and dashboards, so the build focuses on what is specific to you.
After go-live
A system only pays off when people use it every day. That is why we handle all the hand-holding ourselves: training each team on the screens they will use, sitting with them through their first live days, and staying close afterwards to make sure what we built is being used properly by the right people.
Hand-holding, training and aftercare
Role-wise training. Sales, stores, accounts and management are each trained on their own module, using their own data.
On-the-floor support at launch. We stay with your team during the first days of live use, so questions are answered on the spot.
Usage check-ins. In the weeks after go-live we review how each team is using the system and retrain or adjust wherever work is slipping back to Excel, registers or WhatsApp.
Training for new joiners. When new staff join, we help get them up to speed.
Go-live is not the end of the project. We stay on as your technology partner, fixing issues, making small changes and adding reports as your team asks for them. Hosting and support are covered by one fixed yearly charge. When the business grows, new modules are added to the same system, so nothing has to be rebuilt.
The first few weeks after each module goes live are when most small requests come in: a column added to a report, a change to an approval step, a new alert on WhatsApp. These are part of normal support. Larger additions, such as a new department or a new integration, are planned and dated the same way as the original project, so you always know when they will be ready.
Frequently asked questions
Can an ERP go live in less than 8 weeks?
Yes, if the scope is small. A CRM can go live in about 4 weeks, and a single process can often be automated faster. A full ERP across several departments usually needs 12 to 16 weeks.
Do all departments go live at the same time?
No. We go live module by module. Each department is trained and switched over when its module is ready, which lowers risk and gets parts of the business onto the system weeks earlier.
Do we have to stop work while data is migrated?
No. We agree a cut-over date in advance, move in your masters and opening balances, and the team switches from the old sheets to the new system on that date.
How involved does our team need to be?
The owner and department heads join discovery, review a working demo every two weeks, and make staff available for training at launch. One person who can make decisions keeps the project on schedule.
What do we need to prepare before the project starts?
Time with the owner and each department head for discovery, copies of the sheets and reports you use now, and one person on your side who can make decisions. It also helps to start tidying your customer, product and vendor lists early, so they are ready to move in at launch.
Can the ERP connect to Tally?
Yes. We can sync sales, purchases and payments with Tally, so your accountant keeps working as before while you get live dashboards.
Why do some ERP projects take a year or more?
Large off-the-shelf ERP rollouts often spend months adapting the business to the software and launch every department at once. Building around how you already work, on a proven core, and going live module by module keeps most projects within 8 to 16 weeks.
What happens after the ERP goes live?
We stay on for support, small changes and new reports, covered with hosting by one fixed yearly charge. New modules are added to the same system as the business grows.
How much does ERP implementation cost?
A custom ERP from Faxtor costs ₹2–8 lakh to build, plus one yearly charge of ₹30,000–60,000 for hosting and support. See the ERP implementation cost guide for the full breakdown.